7 Substations of Phase II Auxiliary Project of PKOP Refinery of Kazakhstan Branch were Successfully Powered On

2018-02-26 15:06

7 Substations of Phase II Auxiliary Project of PKOP Refinery of Kazakhstan Branch were Successfully Powered On

On February 21, the B-04 Substation of Phase II PKOP Refinery Project of Kazakhstan Branch was successfully powered on at one time. So far, all the 7 substations of the phase II project have been successfully powered on.
Since the construction of the substations began in succession at the end of 2016, the Project Department has managed 6 civil sub-contractors and 3 installation agencies to carry out construction at the same time. The process spans two winter rain seasons. In June 2017, the Project Department began to focus on monitoring, and took various measures to ensure the timely arrival of 730 switch cabinets supplied by ABB. In addition, the Project Department held special meetings at the end of December to eliminate problems, and finally achieved power transmission for all substations.